By: Sunny Wu(sunny7@juntaiplastic.com)![]()
Post Date: May 13st 2021
Post Tags: MBBR case
| Write at the beginning:MBBR Application field |

Municipal wastewater biological treatment
Aquaculture wastewater treatment

Industrial wastewater biological
New construction and remould upgrade

| Enter the topic,case:A Municipal Wastewater In Anhui |
Customer Requirement: First they design processing capacity 55000ton per day, the process is traditional activaed sludge process, the emission standard is second level. Now they require upgrade to primary A standard.
Solution: Use JUNTAI MBBR process reconstruction scheme as follow:
① Not need to build new aerobic process basin, put the JUNTAI MBBR to originalaerobic process basin; Remould the aerating system, set up the intercept device when effluent.
② Build new anaerobic basin and anoxic basin
Result: MBBR process can reach good treatment effect for ammonia nitrogen and total nitrogen removal.the effluent water quality index can reach up to primary A stanrdad.